Bridge Projects

Rochester VT 73 Bridge 19

Rochester ER BRF 0162(18)

photo of bridge

Project Location

VT 73 Bridge 19 is located in the Town of Rochester in Windsor County on VT 73 over the White River. Bridge 19 is approximately 0.02 miles west of the intersection of VT 73 and VT 100. Rochester Village is approximately 0.6 miles north of the bridge on VT 100.

Project Objective

The Rochester VT 73 Bridge 19 Project will replace a temporary bridge with a permanent bridge.

Existing Conditions

The existing bridge was constructed in the 1930s and rehabilitated in the early 1970s. The bridge was severely damaged in Tropical Storm Irene in August 2011. A temporary two-lane bridge was built in the fall of 2011 in order to reopen VT 73. The temporary bridge does not meet Vermont State Design Standards, including the required turning radius for buses or tractor trailers and the required roadway width to accommodate shoulders.

Bridge Design

The new bridge will be a Steel Plate Girder Bridge with a span length of 130 feet. VTrans Engineering Report - Rochester ER BRF 0162(18) (June 2012) studied alternative methods for replacing the bridge and recommended the Steel Plate Girder Bridge based on constructability and cost effectiveness.

This structure will be replaced over the 2014 construction season using conventional bridge construction methods. Traffic will be maintained on a temporary bridge.

Detour Route

To minimize disruption to the public, a temporary bridge will be installed by the Contractor prior to removal of the existing bridge and Route 73 traffic will be rerouted onto the temporary bridge for the duration of construction of the new bridge.

Target Construction Schedule

Construction is expected to be completed in Summer of 2015.

Contractor

The Contractor for VT 73 Bridge 19 is W. M. Schultz Construction, Inc.

Cost

The four bridge projects in Rochester (VT 73 Bridge 13, VT 73 Bridge 15, VT 73 Bridge 16, and VT 73 Bridge 19) are being completed as a single construction project. Bids were opened on October 25, 2013 and the low bidder was W. M. Schultz Construction, Inc. at $6.4 million.